5. PRE CAST CONCRETE
5. 1 General
5.1.1 Scope of Work
Provide precast concrete panels, materials
equipments,
and
,
labors,
complete, in place, as shown on the drawings, specified herein, and as
evidently required for a complete and proper
installation
of
precast
concrete work .
5.1.2 Related
work Described
Elsewhere
a. Cast in
place concrete b. Concrete
reinforcement
5.1.3
Quality Assurance
The manufacture should demonstrate the ability
to provide the required
quality as specified on the drawings or as directed by the Engineer.
5.2
Submittals
5. 2.1
Manufacturing Data
The Contractor, prior to any work "
shall
submit
to
the
Engineer
the
following items :
a. Complete material
list with their specifications of all items proposed to be furnished and installed for this work.
b. Specifications
and
instructions
for
all
manufactured
materials
and
products going to be used in this work.
c. Laboratory
test reports as required by the Engineer.
d. Shop Drawings showing
complete information for the fabrication and installation of all required
work, which is also suppose to include the following information:
i. Member dimensions and cross section, location, size, and type of
reinforcement and lifting devices use for handling
and erection.
ii. Details inserts, connections, and joints,
including all accessories.
iii. Location
and details of anchorage devices that are to be embedded in other construction,
iv.
Gelded connections by AWS standards,
v. Erection
procedure, sequence of erection, and method for temporary
bracing and staging .
5.2.2
Samples
a. Precast samples approximately 300x300x50mm.
cast
from
the
mix
specified illustrating equality
color and texture
of the proposed surface
finish.
b. Submit samples of east_in gaskets,
anchorages, and other attachments
and accessories if required by the
Engineer.
c. Prior to start of installation, one full-size sample of each required precast concrete unit shall
be
submit
to
the
job
site
for
approval
by
the
Engineer, Acceptable samples may be incorporated in the construction,
d. The Engineer inspect color,
texture, and general condition only
.
Compliance with all other requirements is the exclusive
responsibility of the contractor.
5. 3
Delivery and Storage
a. Deliver the work of this section to the job site in such quantities and at such times as to assure the continuity of the installation.
c. Lift and support
the units at the designed
lift points as shown on the
approved shop Drawings.
d. At no time shall units
be permitted to rest on earth or other staining materials.
e. Units shall be seperated one from another with non-staining
wood strips.
f. Thin or flat elements shall be maintained in avertical position.
5. 4 Protection and Replacements
Use all means necessary to protect", the units from damages and staining
before, during, and after installation.
In the events of damage to the units or any materials
of all other trades, immediately make all repairs necessary to the satisfaction of the Engineer. Where corrective measures are
considered un-practicable or
unsatisfactory, the faulty
work
shall
be
replaced by new units at no additional cost to the Employer.
5.5
Products
5.5.1 General
a. Concreting materials as referred to in section
( 4_2). "
Concrete
Work
".
b. Provide
all reinforcement, necessary, and connection materials required in accordance with the final design as approved "by
the Engineer,
c. All anchors, bolts, dowels, fittings and attachment members
shall be of types indicated on the drawings and as approved by the
Engineer.
d. All the materials
provided under this Article shall meet or exceed the
cfuality specified for similar materials tinker other sections
of these specifications*
e. Those materials not specified tinder those sections,
but requried for a complete and proper installation, shall be new, first quality of their respective kinds, and selected
by
the
contractor
subject
to
the
approval of the Engineer.
5.5.2
Design
a. Provide complete design, calculations, and drawings prepared
and
signed by an engineer properly
licensed to perform such services.
1. ACI 301
2. ACI 304
3. ACI 311
4. ACI 310
5. ACI 347
6. Concrete Reinforcing Steel
Institute
"
Manual
of
standard
Practice" .
7. Prestressed Concrete Institute MILL116
" Manual for Plants
and Production of precast concrete products.
Comply with building code requirements which are more stringent than above. In the event of conflict, the morn stringent provisional shall be govern.
c. Engineer's
review of calculation dees not relieve
the manufacturer of design responsibility .
d. Design modifications may be made as necessary
to
meet
field
conditions and to ensure proper
fitting of work.
Maintain the general design concept as shown without
increasing sizes of members
or altering profile
and alignments, and
as acceptable to the Engineer.
5.5.4 Concrete mixes
a. Preinre
design mixes for each type of concrete required, and secure the Engineer's approval of the proposed design. Design
mixes may be prepared by an independent plant, at precast naiiufacturers option.
b. Design the mix and proportion
of the concrete to attain a minimum
compressive strength of 201 Kg / cm2 when cured and. tested at 20 days in accordance with ASTM C39 with
minimum cement content of305Kg/m3
c. Submit written reports
to the Engineer of proposed
mix at least Relays prior to
start of precast unit production.
d. Mix designed adjustments may be requested
when characteristics od materials,
job conditions weather, test , results, or other circumstances .
warrant laboratory test data for revised mix designs and strength results
must be submitted to and accepted by the Engineer before using
in the work.
5. 6. Equipments
a.
forms shall be constructed of steel, with smooth contact surfaces and free from
any staining effect confirming the
exact design dimension and shapes.
b.
Vibrating
table
shall
be
of
design and. Construction to provide frequency
vibration as required to produce units
of the strength, aggregate distribution,
and, finish specified and defined by the
approved samples and test specimens.
c. Mixers
shall be of type to maintain
even distribution of fine and
coarse aggregate, d. Lifting of precast units shall be done using power equipment
of a type approved
by the Engineer.
5. 7 Fabrication
5.7.1 General
a. mix Materials for concrete in an acceptable drum type batch machine mixer and
as explained in section(4_6) provide
a batch ticket for each batch discharge
and used in work, indicating
project ; Identification name and number,
date, mix type, mix time, quantity,
and amount of water introduced .
b. Ready mix concrete
shall be comply
with requirements of ASTM C94, and as herein specified.
i. Addition of
water to batch will not
be permitted.
ii. During hot weather, or under conditions
contributing
to
rapid
setting
of
concrete, a shorter mixing and delivery time than that specified
in ASTM C94 may be required.
c. Place and secure
all anchors , clips, inserts, reglets,
lifting devices, stud bolts , shear
ties, and other devices
required for handling
and isntalling the precast
units, and for attachment of subsequent items as indicated or specified.
d. Finish units shall be straight
, true to size and shape and within the specified
casting tolerances. Exposed edges shall be sharp, straight , and Square.
e. Dimensional
tolerances shall be + ;- 3rnand for lintels shall be + ;- 6mm. Variation from position in plan + ;- 13mm maximum at any locations. Offsets in ftllgaaent of adjacent members at any
joint shall be 1,5 in any 3000mm run and 6mm maximum .
5.7.2 Curing
Form cure for a minimum of 20 hours. Keep Wet continuously for not less than seven days
after being removed
from the forms. Following this curing period,
allowing this curing period,
allow the units to air dry
for at least four days before being
erected.
5. 7. 3 Surface Finish
Appearance
of the precast units is of primary importance and special attention shall be paid to uniformity color, and texture
b. Finish of unformed
surfaces .
Apply trowel finish to unformed
surfaces unless otherwise indicated , consolidate concrete, bring to proper level with a straightedge, floot and trowel to a smooth,
uniform finish. Apply
scratch finish to precast units which will recieve concrete topping after installation .
5.8 Execution
5.8.1 Inspection
Examine the areas and conditions under which work
of this section will be installed. Correct conditions detrimental to proper
and timely completion of the work. Bo not
proceed until unsatisfactory condition have been corrected.
5. 3. 2 Installations
5. 8. 2. 1 General
Install the work of this section in strict accordance with the approved
shop Drawings, and all partinent codes
and regulations. All cutting, drilling
and welding required
for installation shall be provided.
5. 3. 2. 2 Bracing
Bracing shall be adequate
to resist any dimensional
changes and resist
wind load. They shall be left in place until final connections to the structural frames have been made.
5. 8. 2. 3 Bearing Pads
Install flexible
bearing pads where indicated on the approved shop Drawing, set pads
on level and uniform bearing
surface, maintain in correct position
until precast units are in place.
5. 8. 2. 4 Welding
Perform all welding in compliance with the approved
drawings. All unsatisfactory connections shall
be
replaced
or
corrected
according to the instructions of the Engineer,
5. 8. 2. 5 Grouting
a.
After
precast
units
have
been
placed
and
secured,
grout
open
spaces
at
connections and joints.
Atlall times excerise extreme care to prevent
staining of exposed panel surfaces.
b. Use only grout systems recommended by the manufacturer of the precast
units and approved by the Engineer.
c. Provide
any acceptable method
to retain the grout in place until it is sufficiently
hard to support itself.
Promplly remove
all grout material from exposed
surfaces before it hardens.
5.9 Cleaning
5.10 Plant Quality control
Evaluations
a, The manufacturer shall
provide samples of materials and concrete mixes
as may be requested for
additional testing and evaluation.
b . The strength
of precast concrete
units will be consider potentially deficient if they fail to comply with any of the requirements
which
may
affect
the
strength
including the following conditions:
1. Failure
to meet compressive strength tests requirements.
2. Reinforcement
not conforming to specified
fabrication requirements.
3. Precast units damaged during handling erection. When there is evidence that the strength of precast concrete
units
does
not
meet
specification
requirements, cores shall be drilled for compressive strength determination complying with ASTM G42.
c.
Where core test results
are satisfactory and precast units are acceptable for use, fill core holes
solid with patching mortar, and finish to match adjacent
concrete surfaces.
d.
Defective
units
which
do
not
conform
to
the
specified
requirements
shall
be
replaced with suitable units and corrections shall also be made for any other work
affected by this correction
without any additional cost.
No comments:
Post a Comment