4.10.2 Fixing of reinforcement
The steel reinforcement shall be assembled
to
the
exact
shapes
and
dimensions as approved by the Engineer.
The
rods
shall
have
the
approved cross-sectional area and shall be fixed accurately in the moulds. The ends of all tying wires
shall be turned into the main body of the
concrete and shall not be allowed to project towards the surface. Spacing blocks shall be used to ensure accurate cover to the reinforcement, where necessary, and these blocks
shall be of precast concrete
of a strength at least equal to that of the concrete being placed. They shall be as small as
possible in view of practicality and shall be securely fixed in position
by means of wires to be cast into them.
No temporary
supports
for
the
reinforcement
shall
be
allowed
to
be
incorporated into the finished concrete. At the
time
of
concreting
all
reinforcement shall have been thoroughly cleaned and made free
of all loss rust (crude oil or any other coatings that might destroy or reduce
the bond).
Unless otherwise specified or shown on the drawings, minimum cover shall be determined in accordance
with
ACI 318- 77 as indicated on the
following table:
Description
|
Min. cover thickness
|
||
Cast against and permanently exposed to earth
|
75
mm
|
||
Exposed to earth and weather
|
D16
and smaller
|
40
mm
|
|
D19
- D 25
|
50
mm
|
||
Not Exposed to weather and
|
Slabs and walls
|
D25
and smaller
|
20
mm
|
not in
contact
with earth
|
Beams, girder, columns
|
main bars , ties, stirrups
|
40
mm
|
4.11
Form work
This section
covers the fabrication, erection and removal
of forms and other
necessary work thereof,
including material and design of forms.
All
works, covered by this section
shall conform to ACI 347 or relevant
B.S. standards unless otherwise specified herein.
4.11.1 Design of forms
a.
Forms shall be constructed complete with centering, sleeves
and molds to conform
to the shape, form, line and grade required
and shall be maintained rigid to prevent
deformation
under
load
where
required
forms shall provide for adequate
protection of the precast
units placed within the forms, before
pouring concrete.
b.
Joints
shall
be
leak
proof
and
arranged
vertically
or
horizontally
to
conform to the design pattern.
Forms shall be placed on successive
units for continuous surfaces and fitted to accurate alignment
to secure smooth completed surfaces free from irregularities, In long span, where
intermediate supports are not possible, the form deflection due to fresh concrete shall be compensated for. Members shall have true surfaces
in accordance with desired lines,
planes and elevations. If adequate foundation for shores can not be secured, trussed
supports shall be provided.
c. Form-ties; in general, shall be (snap-tie) type which beak
predetermined points at least 2.5 mm, behind
the finish surface
of the concrete, or type
which can be wholly with drawn. Where
form ties, bolts, or rods are to be completely removed,
they shall be coated with grease, In no event,
either
in interior, exterior, or below_
grade
applications, shall any parts of metal ties be allowed to remain within
2.5cm, of the finished concrete
d.
Form surfaces shall be coated before placing of reinforcement, when oil
is used , surplus oil shall be removed from form surfaces.
All oil stains shall be cleaned from reinforcing
steel before pouring of concrete,
e.
Forms shall not be removed without
the approval of Engineer. This approval shall not relieve the contractor of responsibility
for the safety of the work, the minimum period
of time that must elapse between
the pouring of the concrete and the slackening of the form work shall be as follows:
Type
of Formwork
Minimum period
before removal
more than 16 C°
|
7-
16 C
|
|||
Slabs, beams , girders columns, walls
|
14
days
|
21
days
|
||
24
hours
|
24
hours
|
The removal
of form works
shall in all cases be supervised by an
experienced foreman. All form works shall be removed without
such shock or vibration
as would damage the concrete,
and before the form
works and props are removed the concrete
surface should be exposed, where necessary, in order to ascertain that the concrete
has hardened sufficiently, Any work
showing
signs
of
damage
due
to
premature
loading is to be removed
and entirely reconstructed at the contractor's expense.
4.12
Expansion joints
Expansion Joints shall be formed in walls, Floors,
roofs,
beams
and
foundations where indicated
on drawings. Where specified
or shown on the drawings, expansion Joint in Floor shall
be covered with specified metal covers, Reinforcement, or their embedded items bonded to the concrete
( except dowels in floors bonded on only one
side of joints), shall not be
permitted to extend completely through any expansion joint, Expansion
joints in water retaining structures shall incorporate at raid_depth of the
concrete a pressure resisting PVC water stop and joint fillers
shall be installed as shown on
the drawing.
4. 13 Construction Joint
Unless otherwise specified here in ,
construction joint shall be formed and treated in accordance with ( specification
for
structural
concrete
for
Building), ( ACI 301 _ 72). The position of construction joints shall be arranged to minimise the affect
of shrinkage and construction.
The
following Special requirements apply to the
position of construction joints:
a. In beams and slab .
Construction Joints, other than in cantilevers, shall be located at approximate quarter span
points
from
the
center
line
of
supports.
Construction joints shall not be made in cantilevers, and where
it
is
practicable to do so, the whole of the internal span from which
the
cantilever springs shall be cast at the same
time as the cantilever.
b. In flat slab.
Construction Joints shall be formed at the center
of
supporting
span
approximately.
c. In foundation
At each construction joint,
the surface of the existing concrete
shall be thoroughly roughened
to remove all laitance and other
injurious materials and
wetted before any further
concrete is placed.
All concrete
between construction joints
shall be placed
continuously. In the event of unavoidable delay during concreting, the engineer may require
a construction joint to be made, or other appropriate action taken.
Horizontal and vertical joints
shall be thoroughly wetted and covered
with allayer of mortar immediately before placing new concrete.
4. 14 Finishing
4. 14. 1 General
The finishes
described, below must not cause
any deviation out sid the specified allowable deviation from plumb or level or from alignment, profile grades or dimensions specified
in the paragraph on tolerance. Offsets caused by displaced
or misplaced sheathing, lining or form sections, or by
knots in forms or by other wise defective items shall be checked by direct
measurement.
All other irregularities can be checked by use of straight edges or by use of
templates. Surfaces shall be corrected so as to meet the requirements
specified in the paragraph or tolerances.
4.14.
2 Formed surfaces
Formed surfaces
to be hidden by backfill, plaster or other finish material shall not require treatment
after form removal
except for patching
defective concrete, the filling
of holes and the specified
curing, correction of surface
irregularities shall be required for depression exceeding a limit not affecting
the subsequent finish. Formed surfaces
for exposed walls,
water conduit, parapets, curbs,
stair faces and other areas shall be smooth and regular
when completed. Ridges or lips on exposed concrete shall be removed by tooling , grinding or rubbing.
4.14.3 Fair faced concrete
This type of finish is for surfaces which are permanently exposed to view. Forms to provide this finish
shall
be
faced
with
wrought
tongued
and
grooved boards or plywood or metal
panels
,
arranged
in
a
uniform
approved pattern, free from defects
likely to detract from the general
appearance of the finished surface. This
finished
shall
be
such
as
to
require no general filling of surface pitting,
but fins, surface discoloration and other minor defects
shall be remedied by methods approved by the
Engineer without extra cost to the contract.
4.14.4 Unformed Surfaces
Unformed screeded
finish surfaces to be covered
by-backfill or concrete and surfaces of sub-floors
to
be
covered
by
concrete
floor
topping:
Finishing operations shall include
sufficient
leveling
and
screeding
to
produce flat uniform surfaces.
Unformed floated
finish surfaces not permanently consealed by backfill or concrete and for which other finishes
are not specified, including concrete to be permanently exposed
to view such as outside
decks, floor of sumps,
tope of walls, surfaces of gutters, sidewalks and out side enterance
slabs, when trowelled finishes
are needed, floating shall
be continued until
a small amount of mortar without
excess water is brought to the surface, permitting effective trowelling.
Surfaces to receive mastic
water proofing
or asphalt water
proofing shall not have any prominence likely to cause
damage
or
other
harmful
irregularity. Surfaces irregularities shall be reduced or eliminated
by
grinding, after concrete has hardened.
4.14.5 Chemical Surface hardening
Whene shown on the drawings, a cement mortar
trowelled
finish
or
concrete trowelled finish surface shall be treated with chemical hardener, it shall
be applied to slabs after they are at least 28 days cured, cleaned
and free from dust,
oil, grease and other
foreign matter, and dry chemical hardener shall be applied in accordance with the manufacturer's instructions.
This comment has been removed by the author.
ReplyDelete